Every process settles into a balance between how much work is inside it and how fast that work leaves. Little's Law describes that balance: lead time equals work in process divided by throughput. When an operation releases more work than its bottleneck can finish, output stays the same while inventory and lead time climb, and both cost money. Many manufacturers and shippers carry far more work in process than their operations need. This article shows how to find the right level for yours and put a dollar figure on the excess.

What lead time means

Lead time is the time an item spends in a system, from the moment it enters to the moment it leaves. The system can be any part of your supply chain:

Value-added time, also called touch time, is the part of lead time when the item is being changed in a way the customer would pay for, such as cutting, welding, or assembly. The rest of lead time is waiting: in queues, in batches, in storage, in transit, or for an approval.

A note on terms. In Lean, cycle time usually means the time between finished units, or the time one step takes per unit. Many companies use the same words for lead time. Agree on definitions before you compare numbers across teams or suppliers.

Little's Law

Lead time = WIP ÷ Throughput
which is the same as: WIP = Throughput × Lead time

WIP = average work in process, the number of items inside the system (units, jobs, orders, or dollars)
Throughput = average rate at which items leave the system (per day or per week)
Lead time = average time an item spends inside the system

John Little published the proof in 1961. The law holds for averages over a long enough period in any stable system, meaning work enters and leaves at about the same rate. It makes no assumptions about demand patterns or process times, so it works on a single machine or on an entire supply chain.

Keep units consistent. If WIP is counted in jobs and throughput in jobs per day, lead time comes out in days.

What it means in practice: at a given throughput, lead time moves in direct proportion to WIP. Double the work on the floor without adding capacity and lead time doubles. Releasing jobs early to get a head start adds WIP, so every job in the shop waits longer while output stays the same.

Every process has an equilibrium

A process reaches full output at a certain level of work in process. Below that level, the bottleneck sometimes runs out of work and output drops. Above it, output stays flat because the bottleneck is already busy, and every extra job only adds waiting time.

You can estimate that balance point from two numbers:

Minimum WIP for full output = Bottleneck rate × Raw process time

Bottleneck rate = jobs per day the slowest step can finish
Raw process time = time a job takes from start to finish if it never waits

Hopp and Spearman call this critical WIP in Factory Physics. The fabrication shop in the worked example below finishes 10 jobs a day at its bottleneck, and each job needs 8 hours, or one shift, of processing. In an ideal line it reaches full output with about 10 jobs on the floor. It carries 200.

Output and lead time by jobs in process Output rises until about 10 jobs are in process, then stays flat at 10 jobs per day. Lead time stays at 1 day up to 10 jobs, then rises in a straight line: 10 days at 100 jobs and 20 days at 200 jobs. Output (jobs per day) Lead time (days) 0 5 10 0 10 20 0 0 50 50 100 100 150 150 200 200 Jobs in process (WIP) Full output at about 10 jobs. Past this point, more WIP adds no output. Capped: 100 Today: 200 Today: 20 days, $500,000 in WIP Capped: 10 days, $250,000
Ideal line with a bottleneck rate of 10 jobs per day and 1 day of raw process time, at $2,500 of work in process per job. Real lines bend more gradually near the balance point because of variation. Hover over or tap either panel to read the values.

Real operations need some work in process above the minimum to absorb variation in arrivals, process times, and breakdowns. The leak is the work in process far beyond what that buffer requires. It buys no extra output.

Where the money leaks

For a shipper, the same math applies on the water. Inventory in transit equals daily volume times transit days, so every extra day in the pipeline is another day of goods you have paid for and cannot sell.

Flow efficiency

Lean Six Sigma measures how much of lead time adds value with process cycle efficiency (PCE), also called flow efficiency:

Flow efficiency = Value-added time ÷ Lead time × 100

Measure both in the same units, such as working hours.

How do you know if your number is good? Michael George published typical and world-class flow efficiency by process type in Lean Six Sigma (2002). The fabrication shop in the worked example below starts at 5 percent, half the typical level.

Typical and world-class flow efficiency by process type Typical flow efficiency is 1 percent for machining, 10 percent for fabrication, 15 percent for assembly, 30 percent for continuous processes and 10 percent for transactional work. World-class levels are 20, 25, 35, 80 and 50 percent. The example fabrication shop starts at 5 percent. 0% 20% 40% 60% 80% Flow efficiency (value-added time ÷ lead time) Machining 1% 20% Fabrication 10% 25% Example shop starts at 5% Assembly 15% 35% Continuous 30% 80% Transactional 10% 50%
Source: George, Lean Six Sigma (2002). Hover over or tap a row to see how much lead time falls when a typical operation reaches world class.
View the numbers
Process typeTypicalWorld classLead time cut at world class
Machining1%20%95%
Fabrication10%25%60%
Assembly15%35%57%
Continuous (process industries)30%80%63%
Transactional (order entry, purchasing)10%50%80%

The gap between typical and world class is almost all waiting. A fabrication shop at 10 percent has parts sitting still 90 percent of the time. Raising it to 25 percent cuts lead time by 60 percent with the same machines and people. That is the opportunity: shorter lead times and less cash tied up in work in process.

Lead time = Value-added time ÷ Flow efficiency

At 10%: lead time = 10 × value-added time
At 25%: lead time = 4 × value-added time, a 60% cut

Worked example: a fabrication shop

A manufacturer of steel store fixtures runs one 8-hour shift. Jobs move through cutting, bending, welding, powder coating, assembly, and packing.

InputValueHow it was measured
Throughput10 jobs per dayAverage completions over the last 8 weeks
WIP200 jobsAverage of four floor counts on different days
Value-added time8 hours per jobSum of run times from the routings
WIP value$2,500 per jobMaterial plus labor added so far
Carrying rate25% per yearCost of capital, space, and handling

These figures are illustrative.

Step 1. Calculate lead time

Lead time = 200 jobs ÷ 10 jobs per day
    = 20 working days = 160 working hours

Step 2. Calculate flow efficiency

Flow efficiency = 8 hours ÷ 160 hours = 5%

Each job gets 8 hours of work and spends 152 hours waiting. That is half the 10 percent typical for fabrication.

Step 3. Cap WIP

The shop starts releasing a new job only when a finished job leaves, and holds WIP at 100 jobs. That is still ten times the ideal minimum of about 10 jobs, which leaves a generous buffer for variation. Throughput stays at 10 jobs per day as long as the bottleneck always has work.

Lead time = 100 ÷ 10 = 10 working days = 80 working hours
Flow efficiency = 8 ÷ 80 = 10%
Value-added workWaiting
Before: 200 jobs in WIP20 days
8 hours of work and 152 hours waiting. Flow efficiency 5%.
After: 100 jobs in WIP10 days
8 hours of work and 72 hours waiting. Flow efficiency 10%.
Bars are drawn to scale. The work content stays the same, and the waiting shrinks.

WIP value falls from $500,000 to $250,000. That frees $250,000 of cash and saves about $62,500 a year in carrying cost. Sales can quote two weeks instead of four.

Protect the bottleneck. Find the step with the highest utilization, often welding or powder coating in a shop like this. Keep a small buffer of jobs in front of it so it never sits idle, and cut WIP at the other steps first. If throughput drops after a WIP cut, the buffer in front of the bottleneck is too small.

Shrink batches. Large batches add WIP, because each unit waits for the rest of its batch at every step. The EOQ article balances order cost against holding cost. Little's Law adds the time cost of a large batch. Shorter changeovers make smaller batches affordable.

Why busy equipment creates long waits

Little's Law gives you the average lead time. Queueing theory explains where the queues come from. When jobs arrive at uneven intervals and take uneven times, the average wait at a step climbs steeply as the step gets close to 100 percent busy. Kingman's approximation estimates the wait:

Wait in queue ≈ [U ÷ (1 − U)] × V × t

U = utilization, the share of time the step is busy
V = variability factor = (Ca² + Cs²) ÷ 2
Ca, Cs = coefficient of variation (standard deviation ÷ mean) of time between arrivals and of process time
t = average process time per job
Queue wait by utilization for a step with 1-hour jobs Waiting time rises steeply as utilization approaches 100 percent. With typical variation, a 1-hour job waits about 4 hours at 80 percent utilization and about 19 hours at 95 percent. With half the variation, waits are half as long at every utilization. 0 5 10 15 20 50% 60% 70% 80% 90% 95% Utilization of the step Hours waiting per 1-hour job 80% busy: about 4 hours 95% busy: about 19 hours Typical variation Half the variation
Average wait in queue for a step with 1-hour jobs, from Kingman's approximation. Hover over or tap the chart to read the wait at any utilization.
View the numbers
UtilizationWait, typical variationWait, half the variation
50%1.0 hour0.5 hour
60%1.5 hours0.8 hour
70%2.3 hours1.2 hours
80%4.0 hours2.0 hours
85%5.7 hours2.8 hours
90%9.0 hours4.5 hours
95%19.0 hours9.5 hours

Raising the powder coat line from 80 to 95 percent busy moves about 19 percent more work through it and makes each job wait almost five times as long. Two levers bring the curve down:

Little's Law across the supply chain

On the balance sheet: days of inventory

Days of inventory is Little's Law measured in dollars. Inventory is the WIP, cost of goods sold per day is the throughput, and the result is the average number of days a dollar of stock waits before it sells.

Days of inventory = Inventory ÷ (Annual cost of goods sold ÷ 365)

= $1,200,000 ÷ ($7,300,000 ÷ 365)
= $1,200,000 ÷ $20,000 per day = 60 days

Bringing inventory down to $900,000 at the same sales cuts days of inventory to 45, frees $300,000, and saves about $75,000 a year at a 25 percent carrying rate.

In the import pipeline

Stock on order = Demand rate × Supplier lead time

In the EOQ example, a manufacturer uses 2,000 units a month and waits 2.5 months from purchase order to receipt. On average, 5,000 units are on order at any time, about $150,000 of open purchase orders at the $30 supplier price. This is the same demand-during-lead-time term that sits inside the reorder point. A supplier with a 1-month lead time would cut average stock on order to 2,000 units, about $60,000, and lower the safety stock you need. Compare total landed cost before switching, since a closer supplier may charge more per unit.

How to measure your own lead time and flow efficiency

  1. Pick one product family and map its flow. List every step from order receipt to shipment. A value stream map works well for this.
  2. Count WIP. Count jobs or units at each step, including those sitting in queue. Repeat on a few different days and average the counts.
  3. Measure throughput. Use average completions per day over the last 4 to 8 weeks.
  4. Calculate lead time as WIP ÷ throughput. Check it by tracking start and finish dates for 10 to 20 jobs, and compare both with the lead time you quote customers.
  5. Add up value-added time from routings or a time study, and calculate flow efficiency in working hours.
  6. Improve. Set a WIP cap so new work is released only as finished work leaves. Protect the bottleneck with a small buffer. Cut batch sizes and changeover times.
  7. Review weekly. Track the numbers below and adjust the WIP cap as throughput changes.

KPIs to track

Common mistakes

Want to see where your lead time goes?

KOMPASS maps your value stream and measures lead time and flow efficiency from your own production and inventory data. We then set WIP caps that protect your bottleneck, using Lean Six Sigma Black Belt methods. The first call is free.

Book a Discovery Call →

Further reading

  • Little, J. D. C. (1961). A Proof for the Queuing Formula: L = λW. Operations Research, 9(3), 383 to 387.
  • George, M. L. (2002). Lean Six Sigma: Combining Six Sigma Quality with Lean Speed. McGraw-Hill. Source of the flow efficiency benchmarks above.
  • Hopp, W. J., and Spearman, M. L. (2008). Factory Physics, 3rd ed. Waveland Press. Covers Kingman's approximation and WIP caps.